Project

CONSTRUCTION, modernization, OPERATION, MAINTENANCE, CONSERVATION AND EXPLOITATION OF THE INTERSERRANA HIGHWAY, CONNECTION OF THE MATEHUALA-SALTILLO HIGHWAY WITH THE CD VICTORIA-MONTERREY HIGHWAY, IN THE STATE OF NUEVO LEoN.

Sector: Transport


Last Revision

April 01, 2024
 
Short Name of the Project:
0901 Interserrana Highway: Connection of the Matehuala-Saltillo Highway with the Cd. Victoria-Monterrey Highway
Type of Investment:
Greenfield
Subsector:
Highways / bridges
Asset (s):
 Highway 87 KM-A4 
Contract Currency:
Mexican Pesos MXN
Estimated Investment MXN:

N.A.

Estimated Investment USD:

N.A.

Exchange rate (USD/MXN) used by the Ministry of Finance for the economic plan 2024: $ 17.1
Contract Scope:
  Construction,  Modernization,  Operation,  Maintenance,  Conservation,  Exploitation

DESCRIPTION

The project consists of the construction, reconstruction, modernization and expansion of a high specification A4 type highway, in accordance with the current regulations of the Ministry of Infrastructure, Communications and Transportation (SICT), with four lanes of 3.5 m each, two in each direction, exterior shoulders of 2.5 m each and separation between directions of 1 m; with a total length of 87 km, to connect the MEX-085 Ciudad Victoria-Monterrey Highway with the MEX-057 Matehuala-Entronque Puerto Mexico Highway.

The Interserrana Highway includes the following components:
- Section 1 (15 km): Modernization from the junction with Federal Highway MEX-085 to the beginning of the interserrana zone.
- Section 2 (38 km): New construction of 32 km, 43 bridges, 2 tunnels, 4 stabilizations, 4 emergency ramps and 4 tourist stops. From the beginning to the end of the interserrana zone. This section involves private participation.
- Section 3 (34 km): Reconstruction and widening from the end of the interserrana zone to the junction with Federal Highway MEX-057.
• Sub section 3 A: 18 km of road and 3 road junctions.
• Sub section 3 B: 14 km Road and a river crossing.

LEGAL AND FINANCIAL STRUCTURE

Type of Project
  Public / Private
Selection Process
Public Bid

STATUS

Stage
  Execution
RELEVANT DATES
Execution/Construction Starting Date September 19, 2022
Operation Starting Date May 14, 2024

GEOLOCATION

State(s)
Nuevo Leon   

SPONSOR

Responsive image
Entity
State Government
Department
Gobierno de Nuevo León
Secretaría de Movilidad y Planeación Urbana

ADDITIONAL INFORMATION

Responsive image
Source
State Government

REMARKS

On Nov.10, 2023 the call for the structuring and, where appropriate, implementation of section 2 was published.
On April 7, 2024, construction began on section 3B (16 kilometers).
On April 8, 2024, the first 4 kilometers from San Roberto to Galeana became operational.

Section 1: Montemorelos and Start of the distributor on the National Highway.
Section 2: In preparation of executive project.
Section 3A (18kms): In Galeana, progress of 68%
Section 3B (16 km): Completion date is February 2025.

Follow the Project